Laying over concrete or over joists
The substrate decides the product, the fixing method and how much of the budget goes on preparation.
Timber going over a suspended timber floor and timber going over a concrete slab are two different jobs with different risks.
Over joists
A traditional suspended floor gives you something to nail into, which is the simplest and most forgiving fixing there is. Solid tongue and groove boards secret nailed through the tongue into joists at 400 or 450 centres is how most Wellington villa floors were built and it works.
The things to check are joist spacing, whether the joists are level, and whether the subfloor space is dry and ventilated. Boards laid over a damp subfloor will cup regardless of how well they were fixed.
Where an existing floor is sound and you are laying over it, the new boards should run at ninety degrees to the old ones so the joints do not line up.
Over concrete
Concrete brings moisture up. A slab that feels bone dry can be releasing water vapour continuously, and timber laid onto it without a barrier will take that up and move.
Moisture testing comes first, and it needs to be a proper measurement rather than a hand on the slab. A relative humidity probe in a drilled hole gives a real reading. A newly poured slab needs months to reach a level where timber can go on it, and no amount of hurry changes that.
With the reading in hand, the options are a liquid applied damp proof membrane, a sheet membrane under a floating floor, or an engineered board glued down with an adhesive that doubles as a moisture barrier.
Solid timber directly onto concrete is a poor idea in most cases. Engineered board handles it far better because the cross bonded core resists the movement.
Levelling
Concrete is rarely as flat as it looks. Most manufacturers want a tolerance of about 3mm over two metres, and few slabs meet that without work.
Self levelling compound fixes it and is often the largest single line in the preparation cost. It is also the part most likely to be left out of a cheap quote, which is why a floating floor over an unprepared slab develops flex and clicking at the joints within a year.
Height and thresholds
Anything laid over an existing floor raises the level. That affects the clearance under every door, the step at every external threshold, the height of the bottom stair riser, and whether your dishwasher will come out again.
Work those through before committing. Doors can be trimmed. A dishwasher trapped under a benchtop by a 15mm rise is a more annoying problem.
Underfloor heating
Timber over underfloor heating needs a product that tolerates the cycling, which means engineered board rather than solid, and a maximum surface temperature specified by the manufacturer.
The heating needs commissioning and running through a warm up cycle before the floor goes down, then keeping off for a period afterwards. Skipping that is the reliable way to get gaps.